Measure the resistance of the heating circuit and the insulation
resistance and record the measured values in the certificate of
warranty.

Draw the scheme of the heating cable layout in the certificate of
warranty.

Cover the cable with a concrete layer. The concrete layer must be
monolithic so that individual layers do not separate due to thermal
stress.

Measure the resistance of the heating circuit and the insulation
resistance again and record the measured values in the certificate
of warranty.

The concrete mixtures must contain ingredients protecting it
against external effects.

Proveďte proměření odporu topného okruhu a izolačního odporu,
hodnotu zapište do Záručního listu.

Zakreslete do záručního listu rozložení kabelu.

Kabel zalijte vrstvou betonu. Betonová vrstva musí byt monolitic-
ká aby vlivem teplotního namáhaní nedošlo k odtržení jednotli-
vých vrstev.

Opětovně proveďte proměření odporu topného okruhu a izolační-
ho odporu, hodnotu zapište do Záručního listu.

Betonové směsi musí osahovat příměsi chránící směs před vnější-
mi vlivy.

Installing into concrete / Instalace do betonu

1)

Tiles (concrete)

/ Dlažba (beton)

2) Regulation / Regulace EBERLE EM 524 89/90
3)

Fine washed sand,

/ Jemný plavený písek

4)

Concrete layer

/ Betonová vrstva

5)

Ecofloor heating cable

/ Topný kabel Ecofloor

c) Installing into fine washed sand

Procedure (suitable only for use under pedestrian side-
walks)

Create a compact underlying layer of gravel 150–300 mm thick.
This can be regarded as the thermal insulation. You can find
information about the effect and importance of high quality ther-
mal insulation (e.g. on the basis of extruded polystyrene) on the
FENIX internet pages – category ECOFLOOR/Outdoor applica-
tions, or you can consult a technician regarding its use.

Cover the gravel layer with compact sand 5 cm thick.

Place the heating cable in an open-looping pattern in accordance
with the required output. Use Grufast fastening strips to fix the
cable.

Measure the resistance of the heating circuit and the insulation
resistance and record the measured values in the certificate of
warranty.

Draw the scheme of the heating cable layout in the certificate of
warranty.

Cover the heating cable with a 5 cm layer of sand, then place the
tiles.

Measure the resistance of the heating circuit and the insulation
resistance again and record the measured values in the certificate
of warranty.

c) Montáž do jemného plaveného písku

Postup (vhodné jen pod chodníky pro pěší)

Vytvořte zhutněnou podkladovou vrstvu štěrku 150 - 300mm,
vrstvu štěrku můžete považovat za tepelnou izolaci. Vliv a vý-
znam kvalitnější tepelné izolace (např. na bázi extrudovaného
polystyrenu) naleznete na internetových stránkách společnosti
FENIX – kategorie ECOFLOOR/Venkovní aplikace, případně její
použití konzultujte s technikem.

Na vrstvu stěrku vytvořte 5cm vrstvu zhutněného písku.

Rozviňte topný kabel ve tvaru meandru, dle požadovaného výko-
nu. K fixaci kabelu použijte pásku Grufast.

Proveďte proměření odporu topného okruhu a izolačního odporu,
hodnotu zapište do Záručního listu.

Zakreslete do záručního listu rozložení kabelu.

Na topný kabel vytvořte 5cm vrstvu písku, doložte dlažbu.

Opětovně proveďte proměření odporu topného okruhu a izolační-
ho odporu, hodnotu zapište do Záručního listu.